A developer in Brno-Bystrc approached Skymax Living with a request to build 12 terraced houses with a 4+kk layout. The key requirement was maximum efficiency — the identical design of all houses enabled the advantages of serial production of LGSF panels to be utilized.

Advantages of Serial Production

When building multiple identical or similar buildings, LGSF technology offers a fundamental advantage: serial production of panels. CNC machines produce all profiles at once, which significantly reduces the cost per unit.

Economics of Series Production: When manufacturing 12 identical panel sets, production costs decreased by 18% compared to individual production. Total savings including assembly reached 25%.

Project Schedule

Phase LGSF (actual) Masonry (estimate)
Design + BIM 3 weeks 4–6 weeks
Panel Production 4 weeks (all 12)
Foundations 3 weeks 4 weeks
Shell Construction 8 weeks 24–30 weeks
Finishing Works 12 weeks 16–20 weeks
Total 8 months 16–20 months

Project Results

All 12 houses were completed and handed over to buyers within 8 months from the start of construction. The developer especially values: